Skip to main content

ATG Turnouts Installation

Project Launch

September 2012 (First Training) in Switzerland

First installation HYDROSTAR:
April 2013

Project status:
4 turnouts in full operation since July 2013

Project Overview

43 turnouts:

  • 10 turnouts on slab track, 33 on ballasted track
  • 2 perspective turnouts
  • 8 different geometries
  • Setting levels: 168 ZV, 60 HB, 168 IE 2010

Installation locations: north, south and 2 mfs inside the tunnel