Blast furnace 1 in Donawitz: Temporary relining successful thanks to outstanding commitment and teamwork 3 分钟阅读时长
Working environments

Blast furnace 1 in Donawitz: Temporary relining successful thanks to outstanding commitment and teamwork

Christopher Eberl
Holds editorial responsibility for career topics and for the apprentice website. His stories offer insights into the world of work at voestalpine.

The extended intermediate relining of blast furnace 1 in Donawitz was not without its challenges. But these challenges were successfully overcome as a team. After just 64 days, the blast furnace was blown-in on schedule in the end of summer 2018.

Even in Donawitz, last summer was one of the hottest on record—partly due to the high temperatures and partly because of the high demands of carrying out an extended intermediate relining, a feat that made the teams in the plant work up a sweat.

Commitment to excellence

“This wasn’t a normal intermediate relining, it was an extended intermediate relining—a first for us,” says Project Manager Christoph Leitner. The work was much more extensive than with the previous intermediate relinings, but time was the limiting factor. Blast furnace 1 is a key piece of equipment and every day that it stands still costs quite a bit of money. “So we optimized our work packages and did some things in parallel, like setting up several working platforms one above the other in the blast furnace,” says Christoph Leitner. New cranes and additional safety technology also helped shortened the “critical path”.

Everything on schedule

The concept was a complete success. Planning began in April 2017. The blow-down took place on July 21, salamander tapping one day later and on September 25, blast furnace 1 was blown in again. A short time later it was in full operation and since then it has been tirelessly melting hot metal, over 2,000 tons a day. The extensive work packages for the extended intermediate relining were completed on time and in the expected quality (see box). On peak days, up to 250 men were bustling around blast furnace 1.

Bustle throughout the plant

The project team, construction, blast furnace operations, maintenance, logistics and the many partner companies all pulled together. Other areas of the plant took advantage of the blast furnace shutdown to carry out extensive repair work. The second blast furnace in Donawitz, blast furnace 4, was operated at maximum capacity to help compensate for the loss of hot metal from blast furnace 1. “We added oxygen and HBI from Texas to increase the melting capacity,” says Arno Habermann, Head of Reduction Metallurgy. Like we said, last summer in Donawitz was one of the hottest ever recorded.

Hochofen Zwischenzustellung

The project team in front of blast furnace 1.

"This intermediate relining was definitely a challenge—we modernized and partly renewed the entire electrical system. Our schedule was extremely tight, and we only met it because all areas worked very closely together."
Roland Helm, responsible for electrical/instrumentation and control technology
Helm Roland

Roland Helm, responsible for electrical/instrumentation and control technology

"I’m proud of the entire team; we really stepped on the gas. A whole year earlier, we started making use of the short blast furnace shutdowns to carry out preliminary work since speed was of the essence."
Ömer Aydin, Backup Project Manager and Head of Electrical/Instrumentation and Control Technology
Aydin Ömer

Ömer Aydin, Backup Project Manager and Head of Electrical/Instrumentation and Control Technology

"It was a twofold challenge. A lot was renewed on and in blast furnace 1, and blast furnace 4 was run at top capacity. However, collaboration worked very well and despite the time pressure, everyone was very respectful and appreciative."
Manfred Braun, Head of Blow-Down and Salamander Tapping
Braun Manfred

Manfred Braun, Head of Blow-Down and Salamander Tapping

Blast furnace action plan

What’s been done:

  • Blast furnace, stockhouse, skips, casthouse, waste gas cleaning: extensive repairs and maintenance work
  • Renewal of the utilities pipework, electrical, instrumentation and control technology, and automation
  • Renewal of the refractory lining in the taphole area and in the middle area of the blast furnace
  • Renewal of the blast furnace gas pipework and replacement of gate valves
  • Preparatory work for the planned new hot blast stove